Colne Valley Viaduct: Case Study / GRIMSHAW

Colne Valley Viaduct: Case Study
Colne Valley, UK

The Colne Valley Viaduct is a key landmark structure on the High Speed Two (HS2). The design for the 3.4km-long viaduct celebrates the architecture of engineering with a structure that is expressive of power, speed and function. The viaduct has been designed to meet demanding technical, environmental, and operational requirements.

Download PDF

HS2 is a new high speed railway linking London, the midlands and the north, the Colne Valley Viaduct will be a key landmark of HS2 Phase 1 connecting London and Birmingham. It is located in both South Bucks District and the London Borough of Hillingdon, crossing through the Colne Valley Regional Park and continuing into a tunnel under the Chilterns. Construction of the viaduct was completed bin 2025 and ultimately, is planned to be operational from 2029.

The Colne Valley Viaduct is highly responsive to the character of the Colne Valley. Structural spans and pier forms vary as the viaduct passes through a mosaic of lakes and woodland. Over water, extended structural spans of 80m open up the space below the structure, enabling panoramic long-distance views to the landscape beyond. The viaduct requires fixed buttresses to transfer train braking loads into the ground and portals to allow thermal expansion at regular intervals. These have been strategically located at key site features within the Colne Valley. Great care has been taken to express these essential buttresses and portals as visibly special structures, unique to their function and location.

Structural efficiency
High speed trains travelling at up to 320 kmh generate substantial structural loads. A key challenge for the viaduct design has been to accommodate challenging engineering demands while minimising the scale of the structure and reducing impact on the local environment. The design has sought minimise the quantum of concrete and steel by optimising structural efficiency and using faceted forms to shape the structure. The common design language of faceted forms has reduced the volume of concrete required to support the deck above. As a result, embodied carbon has been reduced by over 60%, from a baseline of 195,194 tCO2e to 77,006 tCO2e at completion.

The structure has been designed to achieve a 120 year design life. To achieve this, all materials specified are self-finished to maximise robustness and durability, while avoiding the requirement for long term maintenance or replacement.


Optimised construction
The Colne Valley is a sensitive landscape which has significant environmental considerations including Ancient Woodland, SSSIs, and multiple water-bodies. As such, a variety of sustainable design strategies have ensured impacts on local communities and the environment are minimised.

A key design focus has been to reduce the width of the structure and its construction corridor as far as possible in order to minimise land take. This has limited the impacts on the local environmental, substantially reducing tree loss includingthe avoidance of nearby Ancient Woodland. The construction methodology for the viaduct have been developed in parallel with the design, ensuring buildability is optimised and impacts on the local environment are minimised. Precast concrete deck segments are transported and installed from north to south using a launching girder, minimising construction traffic on local roads and the required construction area. A cantilevered construction method allows the deck to be installed at high level between each pier, reducing disruption to local roads and waterbodies that the structure crosses.

Faceted form and family of components

 

All components have been designed using a common design language to ensure the viaduct is recognisable as a single, coherent structure wherever it is experienced in the Colne Valley. Curvature is only used in the haunched deck profile, where as all other structural components are characterised by faceted forms and defined edges. These folded planes and straight edges characterise the form, alongside textured concrete has been selectively applied to locations where the structure meets the ground.

Improving local accessibility
The landscape design meets strategic place making objectives by responding positively to the character of the area and contributing to local distinctiveness.
A key design strategy has been to increase accessibility to the Colne Valley Regional Park, promoted through enhanced recreational routes and the introduction of new footpaths. The landscape and ecology proposals conserve as much of the most sensitive habitats close to the viaduct as possible. The design establishes new landscape and wetland features, introducing habitats which have been lost in the Colne Valley.

Designing for resilience
Large areas of the Colne Valley are within flood zones. The viaduct design response respects the watercourses, providing a railway that is resilient and does not increase the risk of flooding to other locations. Significant flood attenuation areas have been incorporated within the landscape design, creating substantial wetland areas that contain numerous ephemeral waterbodies, wet grassland, and larger balancing ponds.

Throughout the design process we worked closely with key stakeholders to seek views and ideas to inform design of the viaduct and associated landscape. Align held, a programme of public events which engaged with the local community early in the design process up until the Schedule 17 requests for approval were submitted.

Key

1. Optimised structural efficiency – A fundamental design principle for the viaduct has been to reduce the volume of concrete required by maximising structural efficiency. The variable depth box girder deck locates the primary structure directly below the track, resulting in a more direct transfer of load to the columns below. By optimising structural efficiency, less concrete is required within the viaduct deck, resulting in a structure with less visual mass at deck level and a minimised deck width.

2. Alternative materials – The weight of the deck has been further reduced by using lightweight ultra high performance concrete (UHPC) parapets and a noise barrier system comprised of aluminium acoustic cassettes and transparent acrylic panels.

3. Faceted form – Concrete forms have been carefully crafted and faceted to reduce visual bulk and to achieve a refined and elegant profile. This common language has minimised the volume of concrete required to support the deck above.

4. Re-use – The pier geometry has been designed to enable the re-use of formwork, minimising material usage and wastage. Construction access routes will be re-purposed (including retention of base course materials) to provide multi-functional maintenance and recreational paths along the viaduct route.

5. Comfort / natural daylight – Much of the HS2 route between London and Birmingham is in tunnels annd cuttings, limiting opportunities for natural daylight and long distance views for passengers. Therefore, wherever possible, transparent acrylic panels have been incorporated within the 4m high noise barriers to allow passenger views over the landscape. To enable the use of transparent panels, the noise mitigation performance of the barrier is tuned the precise needs of each location. To mitigate the risk of bird collision with trains, the noise barriers provide effective enclosure whilst the transparent panels incorporate black lines to ensure they remain visible to flying birds.

6. Construction methodology – In order to minimise the impact of construction traffic on local communities and the environment, the precast deck segments are cast on site and transported via a launching girder from the north of the site. They will be constructed piece by piece from high level using a cantilever construction method. The impact on local roads is also reduced with the equivalent of approx. 4000 lorries diverted from local roads via a designated construction corridor including four jetties and a haul road. This construction method also enables the structure to be built over rivers and roads without major impact.

7. Sustainable construction materials – The design team have reduced the carbon footprint of the Colne Valley Viaduct through the replacement of cement with ground granulated blast furnace slag (GGBS). Where possible, the aggregate used in the concrete mix is locally sourced to minimise carbon impact associated with transporting materials.

8. Accessibility – The project will include provision of 3.5km of new footpaths and cycle routes which are fully connected to the surrounding rights-of-way network, as well as opportunities to interact with nature within a range of environments. The network of new recreational routes will open up previously inaccessible areas of the Colne Valley Regional Park to the local community.

9. Enhanced landscape and ecology – The ecological design optimises habitat creation to help deliver local nature conservation objectives. All site soils and substrates have been re-used with profiles matched to the target habitat types. The ecological baseline before starting work has been enhanced through localised changes from species-poor agricultural pasture to a more varied mix of wetland, rich grassland, scrub and woodland.

Key Sustainability Facts

Project Site

Colne Valley Regional Park, Multiple SSSIs and Nature Reserves

Embodied Carbon
  • Overall construction carbon reduction of project = 28.4%

  • Overall embodied carbon reduction = 63,000 tCO2e
    The Scheme Design reduction is in comparison against the Hybrid Bill design used for Parliamentary consent.
Certification

BREEAM Excellent for Infrastructure

Location
Colne Valley, UK

 
Project Partner/Lead
Ewan Jones, Chris Patience

 
Project Team
Grimshaw, LDA Design, Ingerop / Rendel, Jacobs 

Client
HS2 / ALIGN JV

Status
Construction

Year
2024